Bainsford Bridge, Falkirk - Forth & Clyde Canal

Construction Progress at April 2001
Construction Progress at April 2001
Work started in late 1999 with Balfour Beatty building a new bridge to carry Grahams Road over the canal, constructing a new lock to the west of the Grahams Road crossing and deepening the canal between the new lock and existing lock 5. Design was by Fairhurst & Partners, Edinburgh.

The works were completed in May 2001.